Tags
The first phase of the design process, Schematic Design, is now complete. Over the month of the March, the design team, Nunn Construction and the members of the Big Sandy DAG and School Board worked together to complete to reconcile the goals of the project within the limits that have been defined for it, namely the size of the building and the cost of construction.
So key decisions made that allowed the square footage of the school to be reduced to allowed program of 84,300 square feet included reducing the corridors in the classroom wings from 8′-6″ to 8′-0′, reducing the main north south corridor width from 14′-0″ to 10′-0″, reducing the run offs at the ends of the main and auxiliary gymnasiums from 10′-0″ to 8′-0″ and designing the locker rooms to accommodate a specific locker count versus meeting an assigned square footage. In total, these decisions, along with finding a few other small efficiencies reduced the size of the building by over 3,000 square feet.
Key cost reduction decisions made by the DAG and the School Board included limiting the amount of basement under the school. Instead of having a basement and crawlspace under the entire school, basement space will be provided under the locker rooms and under the high school wing. The remainder of the school will be built as a structural floor slab cast to prevent movement due to expansive soils, but will not have crawlspace access. Another significant cost savings decision was to establish that the sloped roofs would have asphalt shingles as a base bid and a metal roof would be bid as an alternate. Over a period of a few weeks, the team was able to make good long term decisions and at the same time, reduced the estimated cost of construction by almost $2,000,000.





































